The RFI That Should Never Have Been Written

The RFI That Should Never Have Been Written

When the answer is already in the drawings, the problem isn’t always missing information. Sometimes, it’s a failure to read, coordinate, and take responsibility.

When the answer is already in the drawings, the problem isn’t always missing information. Sometimes, it’s a failure to read, coordinate, and take responsibility.

11 min read

Construction & Delivery

The RFI That Should Never Have Been Written

When the answer is already in the drawings, the problem isn’t always missing information. Sometimes, it’s a failure to read, coordinate, and take responsibility.

11 min read

When the answer is already in the drawings, the problem isn’t always missing information. Sometimes, it’s a failure to read, coordinate, and take responsibility.

How many RFIs are submitted because something is genuinely missing from the construction documents, and how many are submitted because someone hasn’t taken the time to look?

It’s a question I’ve asked myself more times than I care to remember throughout my career in construction administration.

Requests for Information are an essential part of construction. No set of drawings is perfect, no specification captures every possible condition, and there will always be situations where a contractor needs clarification before proceeding. That’s normal. In fact, a well-written RFI can prevent an expensive mistake, resolve a genuine conflict, and keep construction moving.

But there’s another kind of RFI. The one where the answer is already sitting in the drawings, clearly identified in a detail, noted on a reviewed shop drawing, or spelled out in the specifications.

Those are the RFIs that frustrate me.

Not because I don’t want to answer questions. Quite the opposite. I’d much rather spend my time helping resolve actual construction problems than repeatedly explaining information that has already been provided.

Over the years, I’ve encountered several examples that illustrate how quickly a seemingly minor question can turn into unnecessary correspondence, meetings, arguments, and wasted time.

Three situations stand out.

Conceptual three-panel architectural illustration showing a keyed removable door mullion, two back-to-back furring walls, and the distinction between an approved manufacturer and a specified acoustic ceiling product.

Three construction questions, each with an answer already documented in the reviewed project information.

When the shop drawing already had the answer

On one school project, we had a series of door hardware revisions that included a very specific requirement for removable mullions at several door locations.

Not just any removable mullion. We wanted a keyed removable mullion rather than one that required screws or tools to remove.

“That’s not an information problem. It’s a communication problem.”

“That’s not an information problem. It’s a communication problem.”

“That’s not an information problem. It’s a communication problem.”

During the shop drawing review process, we identified the required hardware and marked up the drawings accordingly. The intent was clear, and those reviewed shop drawings became part of the information the contractor needed to coordinate with the door hardware supplier and installer.

Yet the issue continued to return.

RFIs arrived questioning where the requirement for the keyed removable mullion had been identified. The team had to revisit earlier correspondence, retrieve reviewed shop drawings, and explain the same requirement again.

Eventually, the issue surfaced during construction, after hardware had been installed.

From my perspective, the frustrating part wasn’t the technical question. It was that the information had already been communicated through the review process.

Somewhere between the reviewed shop drawing, the general contractor, the supplier, and the installer, that information hadn’t made it through.

And instead of identifying that breakdown internally, the question came back to the consultant team.

A reviewed shop drawing is not simply another document to file away. Its comments and qualifications need to reach the people responsible for procurement and installation. The contractor remains responsible for coordinating that information through the trades, subject to the applicable contract requirements.

If those comments aren’t communicated, the project can end up questioning decisions that were already made.

That’s not an information problem. It’s a communication problem.

Two walls, one very clear detail

Another example involved a double-height interior space where the architectural intent was particularly important.

We had concrete walls and a condition where the wall assembly needed to continue vertically without creating an awkward step or horizontal ledge at the second floor.

I didn’t want a dust shelf. I didn’t want a change in plane halfway up the space. I wanted one clean, continuous vertical surface.

To accomplish that, we detailed two back-to-back furring walls.

The arrangement appeared in the enlarged plans and multiple building and wall sections. The drawings showed the two physical wall assemblies and how they related to the surrounding construction.

One plan was missing a wall tag, although the wall was identified elsewhere in the documents.

The contractor initially asked for clarification of the wall type.

Fair question.

I’d rather have a contractor ask than make an assumption about an unclear designation. We clarified the intended construction.

But the conversation didn’t end there.

The drywall subcontractor subsequently argued that the second wall wasn’t included in the contract scope and should be treated as an extra.

That’s where a legitimate clarification turned into something else.

The drawings showed two walls. The enlarged plans showed two walls. The sections showed two walls. The design intent and physical arrangement were visible across several documents.

Whether the subcontractor had allowed for that construction in their estimate was a separate issue from whether it was represented in the contract documents.

And that’s an important distinction.

A contractor can legitimately question dimensions, assembly requirements, or conflicting information. Those questions deserve proper consideration. But a pricing omission does not automatically mean the work was absent from the contract.

This is where I believe the general contractor has an important responsibility.

When a subcontractor raises a question, the GC should review it with a fair and reasonable eye. Look at the drawings. Review the specifications. Understand the concern. Determine whether there’s a genuine discrepancy before passing it on.

The RFI process shouldn’t become a mechanism for forwarding every subcontractor disagreement directly to the architect.

Sometimes the right response is to ask the consultant for clarification.

And sometimes the right response is to tell the subcontractor that the work is already shown.

When an approved manufacturer isn’t an approved product

The third example involved acoustic ceiling tiles on another school project.

The specification identified two acceptable manufacturers. However, under the approved products, we had identified a particular ceiling tile because that was the product we wanted.

The drywall subcontractor proposed a less expensive ceiling tile from one of the named manufacturers.

Their argument was straightforward: if the manufacturer was listed as acceptable, then a product from that manufacturer should also be acceptable.

But that wasn’t what the specification said.

There is a difference between identifying acceptable manufacturers and specifying acceptable products. A manufacturer’s name doesn’t automatically make every product in its catalogue interchangeable.

Ceiling tiles can differ in appearance, acoustic performance, durability, reflectance, and other characteristics. Product selection is not necessarily just a matter of choosing the least expensive item from a familiar manufacturer.

We responded by directing the contractor back to the specified product requirements.

That should have resolved the issue, or at least established a clear basis for a properly documented substitution request.

Instead, the discussion continued.

There were additional responses, conversations, meetings, and disagreements about what the specification permitted.

What should have been a straightforward review became a prolonged administrative exercise.

Looking back, I estimate that the issue consumed roughly thirty hours of collective discussion and coordination. That’s my recollection, not a formally tracked project statistic, but it illustrates how much effort a relatively small material dispute can absorb.

And the frustrating part is that all of that time was spent discussing a ceiling tile.

Imagine what else the project team could have accomplished with those hours.

The cost isn’t just another RFI

When people discuss RFIs, they often focus on the number submitted, the average response time, or how many remain outstanding.

Those are useful measurements, but they don’t tell the entire story.

An unnecessary RFI can require someone to retrieve documents, review earlier correspondence, coordinate with consultants, prepare a response, and explain the same information during a meeting.

If the answer is disputed, the issue can return several times.

The original question might take fifteen minutes to answer. The resulting discussion can consume hours.

And that time comes from somewhere.

It’s time that could have been spent reviewing shop drawings, completing field reviews, resolving legitimate construction conflicts, or helping the project move forward.

There’s also a less measurable cost: frustration.

Construction administration already involves competing priorities, changing conditions, and constant decisions. Repeatedly defending information that has already been communicated adds friction to relationships that depend on collaboration.

Over time, it can create an unnecessarily adversarial atmosphere.

The architect becomes frustrated with the contractor. The contractor becomes frustrated with the subcontractor. The subcontractor believes its concern isn’t being heard.

Meanwhile, the project isn’t moving any faster.

The general contractor is more than a forwarding service

I think this is where we need to reconsider how RFIs move through a construction project.

The general contractor has an important coordination role. They’re the connection between the consultant team and the trades performing the work.

That role should involve more than receiving a subcontractor’s question and forwarding it to the architect.

Before an RFI is submitted, someone should be asking whether the issue has already been addressed in the drawings, specifications, addenda, change documentation, or reviewed submittals.

They should also consider whether the question involves a genuine discrepancy, an interpretation of the contract documents, a proposed substitution, or a subcontractor’s pricing concern.

Those are not necessarily the same problem, and they shouldn’t automatically follow the same process.

Of course, consultants have responsibilities too. Drawings need to be coordinated, specifications need to be clear, and responses need to be timely and useful. When information is genuinely missing or contradictory, the design team needs to address it.

This isn’t about suggesting that contractors should stop asking questions.

It’s about asking better questions, after doing the necessary review.

A good RFI should demonstrate that someone has investigated the issue, identified the relevant documents, and explained exactly what remains unresolved.

That’s a much more productive starting point for everyone.

Better communication starts before the RFI

One of the reasons I care about this subject is that it reflects a broader problem in construction: information can exist without actually reaching the people who need it.

A shop drawing can be reviewed without its comments reaching the installer.

“Before sending the next RFI, perhaps the most useful question isn’t “What do we need to ask?” but “Have we already been given the answer?””

“Before sending the next RFI, perhaps the most useful question isn’t “What do we need to ask?” but “Have we already been given the answer?””

“Before sending the next RFI, perhaps the most useful question isn’t “What do we need to ask?” but “Have we already been given the answer?””

A detail can be clearly drawn without being considered during estimating.

A specification can identify a particular product while a subcontractor assumes that any product from the same manufacturer will do.

In each case, the information is available, but the communication or review process breaks down.

Software can help make information easier to find, organize correspondence, and preserve a record of decisions. That’s part of the thinking behind Project Arc.

But software alone won’t solve the problem.

Someone still has to read the documents, understand the intent, coordinate the trades, and take responsibility for passing information along.

An RFI should be a tool for resolving uncertainty, not a substitute for doing that work.

Because the goal isn’t to eliminate RFIs. It’s to make sure the ones we write are worth everyone’s time.

Return to The Arc Journal or explore Project Arc.

SHARE THIS STORY

PASS IT ON.

Share this with someone you build with.

GOOD IDEAS.
WORTH OPENING.

GOOD IDEAS.
WORTH OPENING.

GOOD IDEAS.
WORTH OPENING.

© 2026 Project Arc Technologies Inc.